Divisional
Engineer, Pearse Station, Westland Row, Dublin 2
Innealtoir Rannain Staisiun na Phiarsaigh, Rae an larthair,
Baile Atha Cliath 2 T 01 703 3650 F 01 703 3591 E info@irishrail.ie
W www.irishrail.ie
larnmd Eireann
Deputy T. Sargent T.D.,
Party Leader
The Green Party
35 Main Street
Swords
Co. Dublin
Our Ref: C49/OT.OL/72
9th January 2007
Re: Lady's Stairs footbridge, Ardgillan
Dear Deputy Sargent
I refer to your letter of 27th November.
It had been intended to install a new bridge-deck over both
the railway and the public road on Sunday 3rd December.
Unfortunately due to stormy weather conditions that night
it would have been unsafe to use a crane to lift in the
precast concrete units and the work was postponed.
It is now intended to lift in the bridge-deck units on Sunday
28th January. It will take a further six to eight weeks
to complete the work on the stairs, stair supports and handrails.
Yours sincerely
Liam Meagher
LM/HC
CIE Croup of Companies
|
|
|
|